Site preparation
Site Preparation in Forsyth County: Pads, Driveways, Utility Runs and Staging
Sawnee Land Clearing gets wooded lots in Cumming and Forsyth County ready to build: silt fence and a construction exit first, then clearing, stumps out under the pad, a graded pad, the driveway cut and utility runs, all on one contract. Sites disturbing an acre or more need a county land disturbance permit first.
- Silt fence in first
- Stumps out under the pad
- Pad graded to plan
- One contract
What's included
Everything between the woods and the foundation
Six pieces of work, in the order they happen. We price only the ones your lot needs.
01Erosion control first
Silt fence trenched along the low side and a gravel construction exit at the road, in before the first tree comes down.
02Clearing to the line
Footprint, work margin and driveway corridor cleared. Every tree you flag stays standing.
03Stumps out under the pad
Stumps pulled and holes compacted where the slab and driveway go. Ground flush everywhere else.
04A graded building pad
Level to the plan, cut on the high side and filled on the low side, ready for the builder's stakes.
05Driveway and utility runs
Driveway cut through, with open corridors for water, power and septic so the trenchers don't fight brush.
06Staging and access
A stable laydown area for lumber and trusses, and an exit that keeps clay off the road.

Mature trees add value. We keep the ones you flag.
Keep the good trees
Clear what the house needs. Keep the rest.
Clearing the whole lot is rarely the cheapest or the smartest move. The builder needs the footprint, room to work around it, the driveway and the utility runs.
Past that, the woods can stay, or get underbrushed so you see through the big trees. Trees close to the foundation get their root zones marked so machines stay off them.
- Keeper trees flagged with you on the walk-through
- Root zones near the house marked off
- Septic drainfield area kept unpacked
- Wells and overhead lines planned around
The sequence
First tree to finished pad in about a week of machine time
How a dry week runs on a typical 1 to 2 acre homesite once the paperwork allows work. Wet clay is the usual reason it slips, and we tell you the day we see it.
- 1Day 0
Walk the site
Corners, footprint stakes, keeper trees, the low side and any creek within 200 feet.
- 2Day 1
Erosion control in
Silt fence on the downhill edge and a gravel exit at the road.
- 31 to 3 days
Clear the lot
Brush and small trees mulched, larger trees in the footprint taken down.
- 41 to 3 days
Stumps and pad
Stumps out under the pad and driveway, then a rough-graded, level pad.
- 51 to 2 days
Driveway and corridors
Driveway cut, utility runs opened and the staging area stabilized.
- 6Handoff
Walk it with the builder
Pad, exit and silt fence checked and ready for the next trade.
One contract
One contractor from first tree to finished pad
Site prep touches four trades: clearing, erosion control, stump work and grading. Most clearing outfits do one of them.

Forsyth County rules
The permit math, before anyone books a machine
Most site prep delays come from permit timing, not machines. We sort out which rules apply to your lot on the walk-through.
Permits to clear land in Forsyth County- 1 acre
- Disturbance that triggers the county permit and Georgia's stormwater permit
- 200 ft
- Distance from a creek where even small sites need a permit
- $250
- Forsyth County's listed clearing and grubbing permit fee
- 24 hrs
- Inspection deadline after a half-inch rain on a permitted site
Permit thresholds, fees and buffer widths are those published by Forsyth County and the State of Georgia as of November 4, 2026. Confirm current requirements with the issuing authority before work begins. This is not legal advice.
Cost
What site prep costs, and what moves the number
Site prep is priced from the pieces your lot needs, so two lots the same size can price very differently.
Trunk size and density
Saplings mulch fast. Big hardwoods take longer and may need an excavator.
Stumps pulled or ground
Every stump under the pad comes out. The rest are ground flush.
Slope
Cut-and-fill pads on a hillside take more grading time.
Rock
Weathered rock under the clay slows grading, and nobody sees it until the machine does.
Erosion control
Silt fence length follows the low side of the lot.
Access and haul-off
Narrow drives, gates and anything that must leave the site add time.
Typical ranges around Cumming
- Clearing by mulching
- $1,200 to $6,500+ per acre
- Grading
- $1,200 to $3,500 per acre
- Stump grinding
- $100 to $400 per stump
- Silt fence
- $500 to $1,200 per acre
- Small-lot minimum
- $1,200 to $2,000
Ranges are estimates for Forsyth County and the surrounding area based on job density, terrain, access and acreage. Your written quote is the only price that applies to your property.